News & Updates Construction Updates
We’re proud to report that the construction of Glenlee is well underway. To keep up to date on its progress, register your interest to have updates sent straight to your inbox.
In progress:
Stage 6
Titles estimated: July 2022
View Details85%
Planning100%
Planning100%
Civil Phase89% Site Establishment100% Bulk Earthworks100% Drainage Works100% Sewer Works100% Water & Gas Reticulation100% Subgrade Placement Works100% Electrical & NBN100% Footpaths/Asphalt/Linemarking80% Practical Completion0% Registration Phase7% Statement of Compliance20% Lodge Plan of Subdivision0% Titles0% Settlement0%
Stage 7
Titles estimated: August 2022
View Details76%
Planning100%
Planning100%
Civil Phase78% Site Establishment100% Bulk Earthworks100% Drainage Works100% Sewer Works100% Water & Gas Reticulation100% Subgrade Placement Works100% Electrical & NBN100% Footpaths/Asphalt/Linemarking5% Practical Completion0% Registration Phase5% Statement of Compliance15% Lodge Plan of Subdivision0% Titles0% Settlement0%
Stage 8
Titles estimated: September 2022
View Details39%
Planning100%
Planning100%
Civil Phase37%
Site Establishment100%
Bulk Earthworks100%
Drainage Works35%
Sewer Works100%
Water & Gas Reticulation0%
Subgrade Placement Works0%
Electrical & NBN0%
Footpaths/Asphalt/Linemarking0%
Practical Completion0%
Registration Phase0%
Statement of Compliance0%
Lodge Plan of Subdivision0%
Titles0%
Settlement0%
Stage 9
Titles estimated: Q4 2022
View Details27%
Planning100%
Planning100%
Civil Phase24%
Site Establishment100%
Bulk Earthworks100%
Drainage Works0%
Sewer Works20%
Water & Gas Reticulation0%
Subgrade Placement Works0%
Electrical & NBN0%
Footpaths/Asphalt/Linemarking0%
Practical Completion0%
Registration Phase0%
Statement of Compliance0%
Lodge Plan of Subdivision0%
Titles0%
Settlement0%
Stage 10
Titles estimated: Q4 2022
View Details23%
Planning100%
Planning100%
Civil Phase20%
Site Establishment100%
Bulk Earthworks80%
Drainage Works0%
Sewer Works0%
Water & Gas Reticulation0%
Subgrade Placement Works0%
Electrical & NBN0%
Footpaths/Asphalt/Linemarking0%
Practical Completion0%
Registration Phase0%
Statement of Compliance0%
Lodge Plan of Subdivision0%
Titles0%
Settlement0%
Stage 11
Titles estimated: Q1 2023
View Details3%
Planning50%
Planning50%
Civil Phase0%
Site Establishment0%
Bulk Earthworks0%
Drainage Works0%
Sewer Works0%
Water & Gas Reticulation0%
Subgrade Placement Works0%
Electrical & NBN0%
Footpaths/Asphalt/Linemarking0%
Practical Completion0%
Registration Phase0%
Statement of Compliance0%
Lodge Plan of Subdivision0%
Titles0%
Settlement0%
Stage 12
Titles estimated: Q2 2023
View Details1%
Planning20%
Planning20%
Civil Phase0%
Site Establishment0%
Bulk Earthworks0%
Drainage Works0%
Sewer Works0%
Water & Gas Reticulation0%
Subgrade Placement Works0%
Electrical & NBN0%
Footpaths/Asphalt/Linemarking0%
Practical Completion0%
Registration Phase0%
Statement of Compliance0%
Lodge Plan of Subdivision0%
Titles0%
Settlement0%
Completed:
Stage 1
Completed: September 2020
Stage 2
Completed: September 2020
Stage 3
Completed: October 2020
Stage 4
Completed: April 2021
Stage 5
Completed: October 2021
* Estimated title dates are provided as an approximate guide only and are subject to change.
The title date estimates provided are based on current information regarding the design, construction, and relevant authority approvals timeframes for the individual stage. Glenlee uses this information to provide an estimate of the month (or month/quarter ranges) in which titles will be achieved however this is subject to change and is often influenced by factors which are often outside of the projects control such as weather, contractor delays and authority inspections.